Repairing or replacing a dock after a storm
Re-decking in Cape Coral needs no permit. Replacing framing or pilings does. Florida exempts a same-size replacement dock from a state permit if it stays within 5 feet of the original.
After a hurricane, the first question about a damaged dock is how much of it is left. The answer decides whether you need a permit, a full application, or a new design.
What Hurricane Ian did here
Hurricane Ian made landfall on Cayo Costa on September 28, 2022, as a category 4 hurricane with 130-knot winds. The National Hurricane Center reported maximum inundation of 6 to 9 feet above ground level in Pine Island, Cape Coral, and other communities near the mouth of the Caloosahatchee.
Public docks took damage too. The City of Cape Coral reports that the fishing pier at Yacht Club Community Park was severely damaged by Hurricane Ian. Demolition of damaged park buildings began in April 2024, and the City is redeveloping the park in phases.
Look before you call
A careful look from the seawall, and from a boat or kayak if you can get one, tells you which level of repair you're facing. Check:
- Pilings. Look for lean, cracks, splits at the top, and wood loss near the waterline.
- Stringers and joists. Look under the deck for broken or sagging members and pulled fasteners.
- Connections. Check where the dock meets the seawall cap and where the lift mounts.
- The seawall. Look for cracks, a leaning cap, or soil washed out from behind the wall.
- The lift. If the motor or switch went underwater, keep it off until someone qualified has checked it.
Write down what you see with dates and photos. The list helps you compare contractor assessments, and the photos may help with an insurance claim.
Three levels of repair in Cape Coral
The City's guideline for wood dock repairs, replacements, and additions was revised in January 2026. It sorts work into levels that map to the permit.
| Damage | City permit |
|---|---|
| Deck boards only, frame and stringers sound | No permit for re-decking without replacing the frame or stringers |
| Framing, stringers, or pilings need replacing | Marine Improvement application for repair or replacement |
| Adding area or changing the layout | Marine Improvement application for an addition |
The application for a repair needs the same core documents as a new dock: a site plan, a dock layout, and dock details, plus DEP approval if the lot is not on fresh water. Private providers can't be used.
Florida's replacement exemption
At the state level, Fla. Stat. 403.813(1)(d) exempts the repair or replacement of an existing dock from a state permit if:
- the replacement sits within 5 feet of the same location;
- it is no larger than the original;
- no fill goes in;
- it adds no permanent impact to aquatic resources.
The statute allows different materials and minor design changes for upgrades. Ask FDEP or the contractor whether a change of decking or hardware still fits the exemption.
Find the old dock's survey or permit drawings if you have them. They show the original location and size, which is what the exemption measures against.
The state exemption sits alongside the City permit. You need both answers.
Boat lifts after a storm
Treat the lift as its own item. Wiring for a lift needs a separate electrical permit in Cape Coral. If you plan to reinstall a used lift, the City asks for a Hold Harmless Agreement with the dock application. A replacement lift on an existing dock can use the City's Boat Lift Only permit, though that guideline dates to June 2020; check the current requirements with the City.
Code edition timing
The Florida Building Code 8th Edition (2023) is in force now. The Florida Building Commission's workplan sets the 9th Edition to take effect December 31, 2026. If your repair permit will be filed around the turn of the year, ask the contractor which edition the drawings follow.
Before you hire anyone
Before you sign anything after a storm:
- Photograph the damage before cleanup, from the seawall and from the water if you can.
- Check the contractor's license at MyFloridaLicense.com. For work on Pine Island or Matlacha, check that it is registered with Lee County.
- Ask for proof of insurance.
- Get a written scope that says whether the work is re-decking, a repair, or a replacement, and who pulls each permit.
- Ask whether a Notice of Commencement applies. Under Fla. Stat. 713.135(1)(e), the permit office must receive a copy of the recorded Notice of Commencement before the first inspection when the direct contract is over $5,000. Florida's lien law (713.13, 713.02(5)) applies the notice requirement to improvements over $2,500.
- Don't pay the full amount up front.
For a fuller checklist, see checking a dock contractor.
Outside the city
On Pine Island, Matlacha, Bokeelia, and St. James City, repairs fall under Lee County's Dock and Shoreline permit. A county permit expires if no inspection passes within 180 days of issue, so schedule the work before you pull it. See the Pine Island and Matlacha guide.
Sources
- City of Cape Coral: Wood Dock Addition/Repair/Replace Guidelines, Residential (rev. January 2026) (opens in a new tab)
- City of Cape Coral: Boatlift Only Guideline, Residential (rev. June 2020) (opens in a new tab)
- Florida Statutes, section 403.813 (2026) (opens in a new tab)
- National Hurricane Center: Tropical Cyclone Report, Hurricane Ian (opens in a new tab)
- City of Cape Coral: Yacht Club Community Park (opens in a new tab)
- Florida Building Commission: 2026 FBC Workplan (August 2026) (opens in a new tab)
- Florida Statutes, section 713.135 (2026) (opens in a new tab)
- Lee County: Dock and Shoreline Guide (updated February 26, 2025) (opens in a new tab)
Rules, rates, and costs change. Confirm details with the agency or a qualified professional before you act on them.
Plan your dock
Every dock project starts with the lot: which canal it's on, whether the water is fresh or salt, and which office issues the permit.
(239) 360-6861 Send a requestTide ranges
- Cape Coral Bridge
- 1.14 ft
- NOAA station 8725451
- Fort Myers
- 1.32 ft
- NOAA station 8725520
- Matlacha Pass
- 1.82 ft
- NOAA station 8725506
- St. James City
- 2.40 ft
- NOAA station 8725393
Great diurnal range in feet, from mean lower low water to mean higher high water, on NOAA's 1983 to 2001 datum epoch. Source: NOAA CO-OPS tidal datums (opens in a new tab), retrieved .
Keep reading
-
Cape Coral dock permits: which office, which application
Inside Cape Coral, the City issues dock permits, and DEP approval comes in only when the lot is not on fresh water. Outside the city, Lee County takes over.
-
Checking a dock contractor in Cape Coral and Lee County
Look the license up yourself, know which license classes the City and county accept, and get the scope, permits, and any warranty in writing.
Planning a dock, lift, or seawall?
Describe your waterfront and the project. Your request goes to an independent local contractor, who may call or text you about it.
Areas covered: Cape Coral, FL, Fort Myers, FL, Pine Island, FL, Matlacha, FL, Bokeelia, FL, St. James City, FL.